Ejipura–Koramangala flyover: status and what it means for deliveries nearby

The Ejipura flyover missed its October 2026 target. The new aim is December-end for the main stretch, with the Sarjapur Road ramps next year. What that means for riders in Ejipura, Koramangala and Domlur.

By Editorial team Published

Apply for a delivery job
Delivery riders in helmets waiting at a signal under a flyover at a wide Bengaluru junction after rain

The Ejipura flyover is still not open as of October 2026. Its October-end deadline has lapsed. The Greater Bengaluru Authority's (GBA) internal target is now December-end, and that covers only the elevated stretch between Ejipura and the Kendriya Sadan junction; the entry and exit ramps planned on Sarjapur Road near the Koramangala water tank need fresh land and are expected only next year (Deccan Herald, 5 October 2026). For riders in Ejipura, Koramangala and Domlur, the work zone on the ground stays for now.

For other works around the city, see our road works and closures round-up.

A flyover of missed dates

When What was said Source
Original plan Completion by November 2019 Deccan Herald, October 2026
March 2022 Government cancelled the first contract over financial and execution problems same
15 November 2023 Agreement signed with BSCPL Infrastructure for the remaining work same
October 2025 Deputy Chief Minister D K Shivakumar promised completion by June 2026 Deccan Herald, October 2025
November 2025 GBA commissioner expected it to open by July 2026; 1.35 km of the 2.38-km stretch done Deccan Herald, November 2025
October 2026 October-end target lapsed; December-end set internally for the main stretch; ramps next year Deccan Herald, October 2026

By March 2027 the project will have been under construction for 10 years (Deccan Herald, October 2026). Treat any new date as a target, not a promise.

Why it is still not done

  • Land. In December 2025 the GBA decided to acquire about 7,000 square metres at four places, including parts of St John's Medical College and Hospital, Kendriya Sadan and the Indian Institute of Astrophysics. Engineers then said 584 of the 762 concrete segments had been cast (Deccan Herald, December 2025).
  • Material. A shortage of stone aggregates slowed the work in recent months (Deccan Herald, October 2026).

Riding the area while it's built

The flyover runs over the inner ring road between Kendriya Sadan and Ejipura (Deccan Herald, December 2025), so expect a work zone along that road. What helps on deliveries here:

  • Use landmarks inside the layouts. Our Ejipura page names Indira Gandhi Colony, the Koramangala National Games Village and Ashwini Layout (OpenStreetMap, as of October 2026). For Koramangala it gives 80 Feet Road, Koramangala TTMC and Madiwala Market (OpenStreetMap, as of October 2026). They help when an address is vague, and our Koramangala blocks guide explains the block numbers.
  • Know the morning detour near the water tank. From 6 August 2026, as a trial between 8 am and 10.30 am, the traffic police stopped vehicles from the Sarjapur Road junction and from Ayyappa Junction heading to the Madiwala Police Station junction; the detour runs via Water Tank Junction, Krupanidhi Junction and Madiwala Market Road to Hosur Main Road (Deccan Herald, August 2026). Check whether it is still in force before a morning shift: how to follow traffic alerts.
  • Watch for water after rain. In October 2025, residents told the deputy chief minister that Koramangala 6th Block and Ashwini Layout still flood badly (Deccan Herald, October 2025). Our post on waterlogging and delivery routes has more.

When it opens

The December target covers only the elevated stretch; the Sarjapur Road ramps come later. Expect a squeeze where it comes down: in October 2025, residents asked for the southern end to be extended to Silk Board Junction because of congestion at its narrow landing point on Madiwala Road (Deccan Herald, October 2025). Even after it opens, your drops in Ejipura and the Koramangala blocks are made on the streets below, so the landmarks and detours above stay useful.

Want delivery work in Koramangala, Ejipura or Domlur? Apply for a delivery job.

Topics: Roads South Bangalore

About the author

Editorial team

Our editorial team researches delivery work in Bengaluru, zone by zone, from public sources such as government pages, dated news reports and the companies' published terms.

Ready to ride? One short form, and our team calls you back.

Apply for a delivery job
Apply for a delivery job