Phase 3 of Namma Metro will bring works to two roads: the Outer Ring Road West, from JP Nagar 4th Phase to Kempapura, and Magadi Road, from Hosahalli to Kadabagere (PM India, approved August 2024). As of September 2026, construction had not begun (Oneindia, September 2026). So nothing changes on these roads today, but riders who work JP Nagar, Peenya, Hebbal or the Magadi Road side of the west zone should know what is coming.
For the lines running today and the works already under way, see the Namma Metro guide for riders.
The two corridors
The Union Cabinet approved Phase 3 in August 2024 (Deccan Herald, August 2025). The approval describes two elevated corridors, 44.65 km in all with 31 stations (PM India, August 2024):
| Corridor | Route | Length | Stations |
|---|---|---|---|
| 1 | JP Nagar 4th Phase to Kempapura, along the Outer Ring Road West | 32.15 km | 22 |
| 2 | Hosahalli to Kadabagere, along Magadi Road | 12.50 km | 9 |
The same release names 10 places where Phase 3 is planned to connect with existing metro stations, bus stands and railway stations: JP Nagar 4th Phase, JP Nagar, Kamakya, Mysore Road, Sumanahalli, Peenya, BEL Circle, Hebbal, Kempapura and Hosahalli (PM India). Those are the junctions to watch.
Which of our areas sit on the route
Matched to our area pages:
- JP Nagar: Corridor 1 starts at JP Nagar 4th Phase, also the name of a Pink Line station on Bannerghatta Road (Swarajya, October 2026). JP Nagar is listed as a second connection point.
- Mysore Road: the new station will stand above the existing Purple Line station, with the rail 32 metres up, taller than Jayadeva Hospital station (Deccan Herald, June 2026).
- Peenya and Yeshwanthpur: near Goraguntepalya, the route was changed to a 2.30 km stretch from the Kanteerava Studio flyover to the Yeshwantpur railway yard, linking to the Green Line through travellators proposed between the Peenya and Goraguntepalya stations (Deccan Herald, August 2025).
- Hebbal: a connection point on Corridor 1, which ends at Kempapura (PM India release).
- Vijayanagar: Corridor 2 starts at Hosahalli. Our data lists the Purple Line's Hosahalli station among Vijayanagar's nearest stations (OpenStreetMap, as of October 2026). From there the works will run out along Magadi Road to Kadabagere.
Where the project stands in 2026
- Foundation stone and deadline. The Prime Minister laid the foundation stone on 10 August 2025. Delays in calling civil tenders pushed the deadline to May 2031 and raised the cost by 5% over the original ₹15,611 crore (Deccan Herald, August 2025).
- The double-decker question. The state wants a road flyover built on the same structure as the metro. In September 2026 that plan covered about 37 km, the state had offered about ₹9,700 crore for it, and the Centre had not cleared it. The approved project already has about 3 km of double-decker at two junctions: about 1.4 km at the Kanakapura Road and Outer Ring Road junction and about 1.6 km at Kamakya junction (Oneindia, September 2026).
- Tenders. BMRCL invited tenders in three packages, but they had not been opened by September 2026, and a change in the double-decker plan could mean fresh tenders and more delay (same Oneindia report). In June 2026 Deccan Herald reported that tenders had been floated for only 18.581 km (Deccan Herald, June 2026).
In short: the route is fixed, the start of road works is not.
What metro works usually do to roads
Phase 3 hasn't reached the road yet, but recent metro works show the pattern:
- Long one-way stretches. Bannerghatta Road from Dairy Circle Junction to the Indian Christian Cemetery near Hosur Road was one way for nearly four years while two underground Pink Line stations were built (Deccan Herald, October 2025).
- Night closures with set detours. Metro work shut the Marathahalli Bridge to traffic between midnight and 3 am on three nights in March 2026, with the traffic police listing alternative routes (Deccan Herald, March 2026).
- Slow repair afterwards. Months after Bannerghatta Road reopened, full asphalting had still not been done (Deccan Herald, April 2026).
What that means for you once Phase 3 works start:
- Learn the side roads now around the junctions on the list above, while the main road is still open.
- Call the customer if the map route runs into a closed lane, instead of guessing a way round.
- Don't take the wrong side of a divided road to get round barricades.
- Watch the news before night shifts near the Outer Ring Road West and Magadi Road.